Budget Information

SR 104 - Hood Canal Bridge - Special Repair

Status

October 2017

 
  • Drivers are strongly advised to sign up to receive automated messages for up to the minute bridge information.

Why is WSDOT replacing the bridges' internal mechanics that are responsible for opening and closing drawspan?
The existing lower and upper gear boxes are worn and near the end of their lifespan. Beginning the spring of 2017, contractor crews will replace the Hood Canal Bridge's gear boxes, hydraulic hoses and adjust and align the guide rollers that are responsible for operating the drawspan for marine traffic.

This work requires crews to take precise measurements of the internal mechanical systems that operate the drawspan. In order to take these measurements, crews need to have little to no tidal influence on the bridge. Much of the work is coordinated to occur during night slack tides when there is little water movement and light winds. In order to have the least amount of impact to traffic, we generally limit closures during overnight hours.

Closure information will be available on this web page and the Olympic Region Weekly Construction and Traffic Updates web page. 

Federal law requires the Hood Canal Bridge, and other movable bridges along navigable waterways, to give marine traffic the right-of-way over vehicular traffic.

The End Result
New gear boxes and other internal mechanical parts will allow WSDOT to maintain the functionality of the bridge drawspan and minimize unscheduled impacts to motorists and marine traffic.

Project Benefits
Access - With no convenient alternate routes between Kitsap and Jefferson counties, repairing the bridge preserves an important lifeline for residents and businesses.

What is the project timeline?

  • Oct. 2016 - Project awarded to Northbank Civil and Marine, Inc.
  • Spring 2017 - construction begins
  • Fall 2017 - construction complete

Financial Information

Financial Data for PIN 310439C
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $5,189
CWA $0
Total $5,189

Project signage will reflect the cost of construction engineering, project bid award and sales tax.

How can I get more information?
Contact:
Michele Britton
Project Engineer
360-874-3010

Claudia Bingham Baker
Communications Manager
360-357-2789